Skip to content
AAA CONSTRUCTION Request a quote

West Bay Road · Commercial

Seven Mile Beach Condominiums

Size
84,000 sq ft
Year
2019
Role
General contractor
Wind
Cat 5 / 200 mph
Location
West Bay Road

The challenge

Forty-eight units on a constrained West Bay Road site, with a working hotel either side. No road closures were available and deliveries had to clear the corridor before the resort day started.

The solution

Sequenced the pour schedule around a 6am delivery window and staged materials off site, trucking in daily. Formwork was cycled floor to floor to hold the concrete programme without expanding the site footprint.

The result

Topped out on schedule with no road closure and no complaint filed by either neighbouring property.

More work

All projects

George Town

George Town Business Park

Two office buildings and associated works, built to let while the first tenant was already signed.

YEAR 2018 ROLE General contractor